Dyneley House Surgery - B82053 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month December 2023 | GP2GP transfers received 31 | Integrated within 3 days 35.5% | Integrated within 8 days 48.4% | Not integrated within 8 days (paper copy requested) 16.1% |
Month November 2023 | GP2GP transfers received 33 | Integrated within 3 days 63.6% | Integrated within 8 days 30.3% | Not integrated within 8 days (paper copy requested) 6.1% |
Month October 2023 | GP2GP transfers received 32 | Integrated within 3 days 65.6% | Integrated within 8 days 34.4% | Not integrated within 8 days (paper copy requested) 0% |
Month September 2023 | GP2GP transfers received 26 | Integrated within 3 days 92.3% | Integrated within 8 days 7.7% | Not integrated within 8 days (paper copy requested) 0% |
Month August 2023 | GP2GP transfers received 23 | Integrated within 3 days 60.9% | Integrated within 8 days 39.1% | Not integrated within 8 days (paper copy requested) 0% |
Month July 2023 | GP2GP transfers received 58 | Integrated within 3 days 79.3% | Integrated within 8 days 20.7% | Not integrated within 8 days (paper copy requested) 0% |
Data updated: January 2024
New data is added around 15th of each month